Russia-Turkey Natural Gas Pipeline

Renewal and Expansion of Russia-Turkey Natural Gas Pipeline ; The scope of works included engineering, procurement, construction, installation, pre-commissioning and commissioning for 118.5 km. 36″ high pressure natural gas pipeline complete with 3 no’s of 36″ line valve stations and 48.3 km. 24″ high pressure natural gas pipeline complete with 2 no’’s of 24″ line valve stations.In addition, displacement of 6.4 km. 36″” natural gas pipeline in Pendik-Kurtköy and 4 no’’s of 20″ hot-tap operation, 4 no’’s of 24″ hot-tap operation and 4 no’’s of 36″ hot-tap/stopple operation were carried out within the scope of the Project. (EPIC)